Monday, December 16, 2019

Amelia Earhart Boulevard to Tilton Road (CR 563) Ramp – Phase 5  

Amelia Earhart Boulevard to Tilton Road Ramp

Project: Amelia Earhart Boulevard to Tilton Road (CR 563) Ramp – Phase 5
Cost: TBD (Project currently out to Bid)   
Designer: WSP USA, of Lawrenceville, New Jersey
Contractor: TBD (Bids for said project were advertised April 18, 2018)
Schedule: Substantial Completion – TBD

Project Description:

The fifth and final phase of construction will be the Amelia Earhart Boulevard to Tilton Road Ramp Project.  This project is funded by not only the SJTA and the FAA Tech Center, but also Atlantic County.  The project will include a new roadway from Outbound Amelia Earhart Boulevard to Northbound Tilton Road (County Route 563) heading toward Egg Harbor City and Galloway Township.  The project will greatly improve congestion at Amelia Earhart Boulevard and the Delilah Road / Tilton Road Circle.  The project consists of construction of a new roadway and requisite storm water management facilities.  The project is expected to be completed in December 2018.